Energy Beyond the Grid: Gas Turbines, Nuclear Restarts and the Race for Private Power
The grid cannot connect new gigawatts fast enough for AI. So the builders are bringing their own power: fleets of gas turbines next to data centres, shut-down nuclear plants brought back to life, deals for reactors that do not exist yet, and fuel cells by the hundred megawatts. This guide compares every option on speed, cost, carbon and risk, follows the biggest projects, and asks who pays when data centres leave the grid, or stay on it.
โก Why leave the grid?
The Power Bottleneck explained why AI's appetite for electricity collides with grids built for slow growth. In 2026 the collision is visible in prices and queues. In PJM, the grid operator serving 13 US states and Washington DC, the capacity price that pays power plants to be available rose from $28.92 per megawatt-day for 2024/25 to $329.17 for 2026/27. The 2028/29 auction cleared at the federal price cap of $325 and still came up 6,831 MW short of the reliability target. PJM's market monitor attributes $6.3 billion, 38% of the latest auction's $16.4 billion cost, to data centres.
Waiting years for a grid connection is not an option for companies racing to train the next model. So developers have begun building their own power plants on site, known as behind-the-meter generation, and signing deals to revive or build nuclear capacity.
๐ฝ๏ธ The power menu
โ๏ธ Compare the options
Click an option. Ratings (more bars = better) are our qualitative summary for a US AI campus in 2026, not engineering estimates.
๐ฅ Gas: the fast answer
Natural gas turbines can be installed in months to a couple of years, run around the clock and sit right next to the servers. Cleanview's 2026 tracker counts about 101 GW of behind-the-meter gas generation announced for US data centres, of which more than 57 GW has disclosed equipment orders and about 7 GW is under construction. Texas alone accounts for about 38 GW. Only around 2 GW was actually operating by mid-2026, most of it at one company.
๐ From announcement to electrons
US behind-the-meter gas for data centres, gigawatts. Announced totals include speculative projects.
Cleanview, "Bypassing the Grid" (mid-2026). Operating figure: ~2 GW across four projects, mostly xAI.
- xAI, Memphis
- The pioneer. Colossus 1 and 2 near Memphis account for about 1,498 MW of operating gas turbine capacity, with dozens of temporary mobile turbines added at the Southaven site across the state line. Cleanview projects total behind-the-meter capacity of 2.8โ3.2 GW by the end of 2026. The turbines have drawn local opposition over air pollution.
- Stargate, Abilene
- Crusoe's campus for OpenAI in Abilene, Texas, with power demand of about 1.2 GW, uses aeroderivative turbines adapted from jet engines, which start fast and come in smaller units.
- Others
- Developers in Texas, Ohio, Pennsylvania and the Southwest plan gas plants sized from hundreds of megawatts to several gigawatts, often with the option to connect to the grid later.
โป๏ธ Nuclear restarts: bringing plants back
The fastest route to large amounts of clean, round-the-clock power is to restart reactors that closed for economic reasons. Three US plants are in progress, each backed by a tech company's long-term contract and federal loans: the Department of Energy has committed $4.42 billion across them. As of mid-October 2026, none had returned to service.
๐ ๏ธ Restart tracker
Status of each milestone, October 2026.
American Nuclear Society, Nuclear Newsnetwork, Discovery Alert and company announcements. โ done ยท ๐ก in progress ยท โฌ not yet.
๐ฌ Small modular reactors and advanced nuclear
Small modular reactors (SMRs) promise factory-built units of tens to a few hundred megawatts that could sit near data centres. Big tech companies have signed a wave of deals, but none of these reactors is running yet, and most first units target 2030 or later.
๐๏ธ The deals
| Buyer | Developer & design | Scale | Status (Oct 2026) | First power |
|---|---|---|---|---|
| Kairos Power, molten-fluoride-salt-cooled reactor | 500 MW fleet | Hermes and Hermes 2 demo construction permits (Dec 2023, Nov 2024) | 2030 first unit; fleet by 2035 (sources differ) | |
| Amazon | X-energy, Xe-100 high-temperature gas reactor | Up to 12 units; Energy Northwest project ~960 MW | Amazon invested $700M for rights; fuel-facility licence (Feb 2026); Dow site review advancing | End of decade |
| Meta | Oklo, Aurora fast reactor | 1.2 GW campus, Pike County, Ohio | Prepayment agreement (Jan 2026); no NRC reactor licence yet | Not set |
| Meta | TerraPower, Natrium sodium-cooled reactor with storage | Up to 8 plants | Kemmerer, Wyoming construction permit (Mar 2026) | As early as 2032 |
| Utility (TVA) | GE Hitachi BWRX-300 | ~300 MW unit at Clinch River | NRC construction approval (Sep 2026) | Around 2030s |
SMR Intel, Oklo 10-Q, company announcements, NRC dates via trackers. Meta's total nuclear commitments are reported at up to ~6.6 GW (figures vary).
๐ When does each option arrive?
๐๏ธ Realistic delivery windows for new AI power
Approximate, for projects starting in 2026. Solid = typical window; faded = possible but uncertain.
Our synthesis of the dates reported above; individual projects vary widely.
๐ Fuel cells and the rest
Fuel cells convert natural gas into electricity chemically, without combustion, so they emit almost no local air pollutants (though still COโ), need no air permit in many places and can be installed in modules within months. Bloom Energy has become a major supplier: a 20-year, $2.65 billion agreement with utility AEP signed in January 2026 covers an initial 100 MW with an option to expand to 1 GW, and an April 2026 agreement with Oracle is reported at 2.45โ2.8 GW (sources conflict). Brookfield has committed billions to finance Bloom deployments.
Batteries smooth the spiky power draw of training runs and provide backup. Solar and wind with storage, bought through long-term power purchase agreements, remain the cheapest new energy, but cannot alone guarantee round-the-clock supply. Geothermal (including new enhanced geothermal) offers firm clean power at small scale today.
๐๏ธ Grid politics: who pays?
๐ PJM capacity prices
Clearing price, $ per megawatt-day, by delivery year.
PJM auction results via IEEFA, Enel and the market monitor (Utility Dive). 2028/29 cleared at the $325 cap, 6,831 MW short.
Capacity costs flow into everyone's electricity bills, so the question of who pays for data-centre growth has become political. Regulators are trying to write rules for data centres that build their own generation or co-locate next to existing power plants, which can take clean power off the grid that households rely on.
- Dec 2025
- FERC found PJM's tariff unjust and unreasonable for lacking clear co-location rules and ordered reforms.
- Apr 2026
- FERC partially approved PJM's compliance package, rejecting its revised definition of co-located load.
- Jun 2026
- FERC issued show-cause orders requiring all six US regional grid operators to justify or reform their rules for large loads, rather than adopting one national rule; the large-load rulemaking docket (RM26-4) remains open.
๐งช Build a power plan
๐๏ธ Power a 1 GW AI campus
Choose how many megawatts come from each source. Timings and emission factors are rough, illustrative values.
Assumptions: 1 GW load at 85% average use. Emission factors (t COโ/MWh): gas turbines ~0.45, fuel cells on natural gas ~0.37, average grid mix ~0.37, clean PPA and nuclear ~0. Time to power: fuel cells ~1 yr, gas ~2 yrs (turbine queues), grid connection ~4โ7 yrs, nuclear restart ~2027โ29, SMR ~2030+.
๐ฐ๏ธ Timeline
๐ญ What to watch
- Palisades and Crane: the first restarts to return to service, and whether Crane's grid connection is really delayed to 2031.
- Turbine supply: GE Vernova, Siemens Energy and Mitsubishi capacity expansions, and lead times.
- Air permits and local opposition to on-site gas, from Memphis to New Jersey.
- FERC and grid operators' large-load rules, and PJM's next capacity auction.
- First SMR construction at TVA Clinch River, Kemmerer and X-energy sites, and Oklo's licence application.
- Off-Earth options: see Data Centers in Space for the most radical way to escape the grid.
๐ข Reading the numbers
- Gas totals (101 GW announced) include speculative projects; only ~2 GW was operating by mid-2026.
- xAI capacity comes from Cleanview's tracker; turbine counts change frequently.
- Restart dates are company targets and have slipped before; Palisades' 2026 return is now unlikely per one analysis.
- SMR timelines differ between sources (Kairos 2030 vs 2035) and are very uncertain.
- Fuel-cell deal sizes (Oracle 2.45 vs 2.8 GW) conflict between aggregator sources.
- Ratings and simulator values are illustrative.
๐ References
- Gas and behind-the-meter power
- Cleanview: Bypassing the grid โ how data centre developers are building their own power plants
- RBC Capital Markets: Natural gas powers the data centre boom (May 2026)
- Grist: Data centres are scrambling to power the AI boom with natural gas
- Virginia Mercury: On-site turbines and state renewable laws (Jul 2026)
- Build: Why gas turbines are back in the stack
- datacenterHawk: Behind-the-meter power solutions
- Nuclear
- ANS: NextEra and Google ink a deal to restart Duane Arnold
- ANS: FERC decision on Crane restart (May 2026)
- Nuclear Newsnetwork: Nuclear plant restarts tracker
- Discovery Alert: The restart race, October 2026
- SMR Intel: Every nuclear-powered data centre deal
- SMR Intel: State of small modular reactors 2026
- Fuel cells, grid and policy
- Bloom Energy Q2 2026 results (8-K)
- Holland & Knight: FERC advances new oversight framework for large loads
- McGuireWoods: FERC show-cause orders to all six RTOs/ISOs
- Beveridge & Diamond: FERC orders PJM to create co-location rules
- FERC: Interconnection of large loads (Docket RM26-4)
- Utility Dive: Data centre load and PJM wholesale costs
- IEEFA: Data centre growth spurs PJM capacity prices by a factor of 10