Project Rainier: The AI Factory Built Without NVIDIA
Every site so far in this series runs on NVIDIA GPUs. Project Rainier does not. Amazon filled farmland near New Carlisle, Indiana with nearly half a million of its own Trainium2 chips and handed the cluster to Anthropic to train Claude. This case study looks at what it means to own every layer from chip to cloud, how a utility created a company just to power data centers, and why residents near the site started checking their wells.
1. Case file
AWS said in October 2025 that Anthropic would be running Claude on more than 1 million Trainium2 chips across Project Rainier and Amazon Bedrock by the end of 2025. Some trackers still list 1 million as a target โ ๏ธ. Press reports of the full build put grid draw at about 2.2 GW.
2. Build timeline
Project Rainier, 2024 โ 2028
Solid dots are confirmed by Amazon, a utility or a public body, hollow dots come from trackers or the press, โ ๏ธ marks claims we could not confirm and dashed dots are planned. Click a dot for its source.
Amazon announced an $11 billion data center campus in St. Joseph County in April 2024, after acquiring farmland around New Carlisle through a company that did not name it. Construction began in September 2024, and according to press reports seven buildings were running within about seven months. AWS declared Project Rainier active in October 2025, less than a year after its public unveiling. In November 2025 Amazon announced a further $15 billion for new campuses in Northwest Indiana, adding 2.4 GW and 1,100 jobs.
3. The bet: own every layer
NVIDIA sells the most sought-after chips in computing, and it charges accordingly. A frontier lab that buys NVIDIA GPUs pays NVIDIA's margin on every chip, and waits in NVIDIA's queue. Amazon's bet is that its own chips, designed by its Annapurna Labs unit, can deliver enough training performance at lower cost to make up for NVIDIA's software lead, and that owning every layer gives it control over supply and price.
4. Who owns each layer
The stack, site by site
Pick a site. Each layer is coloured by whether the site's owner built it in-house or bought it from someone else. Simplified.
5. The chips
Trainium2 is built for training and serving large models. AWS groups 16 chips into a server, then joins four servers into a Trn2 UltraServer of 64 chips with its NeuronLink interconnect, so they act as one large accelerator. UltraServers are linked across buildings by Amazon's Elastic Fabric Adapter (EFA) network into an UltraCluster. For comparison, NVIDIA's GB200 NVL72 joins 72 GPUs in one rack. Head-to-head performance depends heavily on the workload and the software, and neither company publishes a neutral comparison; see custom silicon vs NVIDIA.
Chip count
How many Trainium2 chips Claude runs on, by source. Toggle between what AWS says and how trackers describe it.
6. Spread, not stacked
Fairwater packs GPUs into dense two-storey halls at about 140 kW per rack. Rainier went the other way: a cluster spread across many buildings on a large rural site, and across states. Reports describe the Indiana campus as the primary site, with a smaller campus near Canton, Mississippi, linked by high-speed networks. Spreading out is easier to cool and to build in phases, but pushes more traffic onto the network between buildings, so the cluster design leans on the EFA network rather than on very large single racks.
Two ways to build a big cluster
7. Power: a utility built for data centers
Rainier gets its power from NIPSCO, the northern Indiana utility owned by NiSource. To serve Amazon's growth without loading the cost onto households, NIPSCO set up a separate subsidiary, GenCo, to own new generation for data centers. Circle of Blue called it the first utility dedicated to data centers in the United States. The November 2025 package includes two new gas turbines with a combined 2.6 GW and a 400 MW / 1,600 MWh battery. Amazon pays for any new transmission, and NIPSCO estimates existing customers will save about $1 billion over 15 years. In April 2026 NiSource said it was speeding up energization of Amazon's sites.
How the GenCo arrangement works
Tap a box. Contract terms are summarised from public announcements.
Like Colossus and Abilene, the new supply is mostly gas; unlike them, the turbines belong to a regulated utility rather than sitting inside the data center fence. Related reading: the power bottleneck.
8. Water and taxes
Water. In May 2025 WNDU reported that residents near New Carlisle said their wells were running dry while the Amazon campus and a nearby GM/Samsung battery plant were under construction, and that the Indiana Department of Natural Resources was investigating. A Notre Dame student investigation estimated peak demand on the local aquifer could reach up to 35.5 million gallons a day, about 80% of its safe yield โ ๏ธ. County officials have said water use will be capped and kept within local standards; opponents dispute what cooling system Amazon uses. We found no final state finding on the wells.
Taxes. St. Joseph County approved a 10-year, 50% real property tax abatement on 870 acres and an 85% exemption on personal property such as servers. Officials said Amazon would still pay more than $722 million in taxes over 35 years. In March 2026 some council members asked Amazon to consider giving back part of roughly $4 billion of abatements over 35 years; Amazon had not responded publicly.
9. Four bets compared
| Colossus | Abilene | Fairwater | Rainier | |
|---|---|---|---|---|
| The bet | Speed | Outside capital | Network of sites | Own silicon |
| Chips | NVIDIA H100 โ GB300 | NVIDIA GB200 | NVIDIA GB200/GB300 | Amazon Trainium2 |
| Size (Epoch est.) | ~946 MW | ~421 MW | Atlanta ~636 MW | ~910 MW |
| Power | Grid + own turbines | Grid + gas microgrid | Utility grid | Utility via data-center-only GenCo |
| Main controversy | Turbine permits | Tax breaks, delays | Utility gas plants | Wells, tax breaks |
10. Reading the numbers
- From Amazon
- Nearly 500,000 Trainium2 chips at activation (Oct 2025); more than 1 million Trainium2 chips for Claude by end of 2025 (stated as a plan; some trackers still treat it as a target โ ๏ธ); $11B + $15B; 2.4 GW and 1,100 jobs in the expansion; 64-chip UltraServers.
- From the utility
- GenCo; two gas turbines totalling 2.6 GW; 400 MW / 1,600 MWh battery; ~$1B customer savings over 15 years (NIPSCO estimate).
- Estimates
- ~910 MW IT power now and ~1.9 GW by Q1 2028 are Epoch AI estimates; ~2.2 GW full grid draw and 30 buildings are press figures.
- Contested
- Dry wells (DNR investigation, no final finding found); aquifer stress estimate from a student investigation โ ๏ธ; cooling type disputed by opponents.
- Illustrations
- The stack-ownership chart simplifies who builds each layer.
- Amazon and trackers
- AWS activates Project Rainier
- Epoch AI: Anthropic-Amazon New Carlisle
- Data Center Knowledge: Project Rainier complete
- DataCenterNews: the $11bn Indiana campus
- Measured AI: AWS New Carlisle campus
- Compute Atlas: Project Rainier
- Power
- WSBT: $15B expansion and NIPSCO
- Energy-Storage.News: 1.6 GWh battery and gas package
- Circle of Blue: America's first data-center-only utility
- NiSource expands Amazon contract
- Water and taxes
- WNDU: wells lose water near Amazon, GM projects
- Notre Dame journalism: Data Dominion
- Inside Indiana Business: incentives approved
- DCD: county approves $11bn data center
- WVPE: Amazon declines to discuss renegotiating tax break